House Build

RECENT PROGRESS

1/31 - Ready for move in!!!

1/27 - Final plumbing, electric.

1/10/17 - Garage door, stain/paint, fixtures.





12/12 - Trim, tile, and yard work.



















11/10 - Exterior paint, hardwoods, cabinets, front walk and driveway



10/13 - Siding, insulation, drywall


9/18 - Plumbing and Electrical


8/22 - HVAC, Front Porch, Windows and Doors



8/6 - Roof is on


7/23 - Putting on the second story



6/22 - Framing main level


BEFORE AND AFTERS

Front




Back





Living Room



Old/New Kitchen




Hearth Room




Half Bath

Main Level Only Full Bath/Updated Master Bath


Dormer Attic/Master


Maddie's Room

Graham's Room


Here is the official timeline:
10/30/15 - Signed FSBO Contract with 2/29/16 Close By Date
2/29/16 - Closed on house...cut it down to the wire.
3/15/16 - Begin interior demo.
3/23/16 - End interior demo.
5/2/16 - Plans complete and signed off by engineer.
5/3/16 - Plans submitted for permits.
5/18/16 - Permits approved!!
5/24/16 - Tear off siding and remove patio.
5/31/16 - Dig footers.
6/3/16 - Pour footers.
6/20/16 - Pour porch and garage floor.
6/21/16 - Framing started.
8/6/16 - Roof on.
8/9/16 - HVAC installation and front porch complete.
8/22/16 - Windows and doors installed.
9/16/16 - Rough plumbing and electrical complete.
10/3/16 - Siding on the house
10/7/16 - Drywall hung
11/25/16 - Trim complete
12/6/16 - Tile and countertops installed
12/12/16 - Paint start
1/6/17 - Paint complete